Joget DX 8 Stable Released
The stable release for Joget DX 8 is now available, with a focus on UX and Governance.
Hi, what do you mean by "cannot process"? In any case, if the synchronous deadline triggers first, then it will move on to the next activity or tool already.
I make 2 deadline 1 for asynchronous for the first date and synchronous. This 2 deadline cannot process in my run process. Someone had any idea how to fix this?
first deadline limit : "#date.DAY-1.dd-MMM-yyyy HH:mm[{variable.dueDate}|dd-MM-yyyy]#"
second deadline limit: "#date.DAY-2.dd-MMM-yyyy HH:mm[{variable.dueDate2}|dd-MM-yyyy]#"